Sample report

See exactly what you receive before you commit.

This is the structure of a real Full Constructability Review deliverable. Want the complete redacted PDF sample? Enter your email below.

Get the full sample report PDF

A complete redacted example, delivered to your inbox.

Cover page

Project name, address, client name

Review date and report version

Prepared by: Kane Construction Services Inc.

Documents reviewed (drawing sheet list, dates, revision numbers)

Disclaimer: consulting opinion only, not architectural or engineering certification

Executive summary

Project overview and total issues identified by risk level

High risk Medium risk Low risk

Summary of most critical findings

Recommended next steps before construction begins

Section 1 — Architectural plan review

Floor plan coordination (room-to-room conflicts, dimension discrepancies)

Ceiling height transitions and framing implications

Window and door schedules vs. plan locations

Missing interior details and specification gaps

Section 2 — Structural coordination review

Beam and header locations vs. architectural openings

Load path conflicts (bearing walls, point loads, columns)

Structural drawing vs. architectural drawing conflicts

Section 3 — Framing and enclosure review

Roof framing complexity and coordination with architectural design

Exterior wall assembly — insulation, sheathing, water barrier

Cantilevered or complex framing conditions not detailed

Section 4 — MEP coordination review

HVAC equipment location, duct routing feasibility, clearances

Plumbing stack locations vs. structural framing

Electrical panel location and service entry coordination

Section 5 — Exterior envelope and roofing

Roof drainage, flashing details, and water management

Deck and balcony waterproofing

Exterior cladding transitions and termination details

Section 6 — Budget risk and change order exposure

Allowance items identified — are they realistic for the market?

Scope gaps between drawings and builder proposal

Estimated change order exposure range (qualitative)

Section 7 — Questions for your design and construction team

Specific questions for the architect, by drawing sheet reference

Specific questions for the structural engineer

Items to confirm are included in the GC's scope of work

Appendix

Annotated drawing markups (PDF with comments by sheet)

Risk item log (item, location, risk level, recommended action)

Ready to get this for your project?

Schedule a review →